SOLAR + STORAGE · ERCOT

Pradera Solar

Pradera Solar is a 118 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0056
Grid region
ERCOT (Texas)
Developer
Pradera Solar, LLC
Connection point (POI)
tap 345 kV Lobo (80219) - Fowlerton (5709)
Location
Webb County, Texas
Technology
Solar: 118 MW · Battery
Total requested
118 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
8 July 2021
Proposed online date
March 2027

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County