Seven Flags BESS

Seven Flags BESS is a 103 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2021 (completed)
  2. ConsentedMay 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0351
Grid region
ERCOT (Texas)
Developer
Seven Flags BESS LLC
Connection point (POI)
8295 Wormser Substation 138kV
Location
Webb County, Texas
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
1 September 2021
Agreement signed
19 May 2023
Proposed online date
January 2026

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem