ONSHORE WIND · ERCOT

Bendito Wind

Bendito Wind is a 300 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0117
Grid region
ERCOT (Texas)
Developer
Bendito Wind Farm, LLC
Connection point (POI)
Tap 345 kV80220 Cenizo - 80079 Cruce Ckt 2
Location
Webb County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 July 2025
Proposed online date
July 2029

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem