🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Siete

Siete is a 493 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2018 (completed)
  2. ConsentedJun 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0047
Grid region
ERCOT (Texas)
Developer
Apex Clean Energy
Connection point (POI)
345kV 8718 Triada
Location
Webb County, Texas
Technology
Wind: 493 MW
Total requested
493 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
23 October 2018
Agreement signed
30 June 2022
Proposed online date
January 2028

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem