United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTSiete
Siete is a 493 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.
Queue statusConsented
- PlanningQueued Oct 2018 (completed)
- ConsentedJun 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 20INR0047
- Grid region
- ERCOT (Texas)
- Developer
- Apex Clean Energy
- Connection point (POI)
- 345kV 8718 Triada
- Location
- Webb County, Texas
- Technology
- Wind: 493 MW
- Total requested
- 493 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 23 October 2018
- Agreement signed
- 30 June 2022
- Proposed online date
- January 2028
Location
Marker shows the centre of Webb County; the queue data does not give exact sites.
Other requests in Webb County
- Cuchillas SolarSolar + storage · 306 MW · agreement signed
- Corazon Solar Phase IISolar + storage · 204 MW · agreement signed
- Corvus SolarSolar · 202 MW · agreement signed
- Seven Flags BESSBattery storage · 103 MW · agreement signed
- Cedro Hill Wind RepowerOnshore wind · 9.9 MW · agreement signed
- Torrecillas BESSBattery storage · 9.9 MW · agreement signed
- Outpost StorageSolar + storage · 508 MW · in study
- Siete WindOnshore wind · 493 MW · in study
- Cuchillas BESSSolar + storage · 307 MW · in study
- Cenizo SolarSolar · 301 MW · in study
- Bendito WindOnshore wind · 300 MW · in study
- Miracle Ranch Solar SLFSolar + storage · 222 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem