Torrecillas BESS

Torrecillas BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusConsented
  1. Planning (completed)
  2. ConsentedJan 2015 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0529
Grid region
ERCOT (Texas)
Developer
Torrecillas Interconnect, LLC
Connection point (POI)
161257 Torrecillas 345kV Station code: TORR
Location
Webb County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
IA Executed
Queue status
Active
Agreement signed
30 January 2015
Proposed online date
February 2026

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.