BATTERY STORAGE · ERCOTTorrecillas BESS
Torrecillas BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.
Queue statusConsented
- Planning (completed)
- ConsentedJan 2015 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0529
- Grid region
- ERCOT (Texas)
- Developer
- Torrecillas Interconnect, LLC
- Connection point (POI)
- 161257 Torrecillas 345kV Station code: TORR
- Location
- Webb County, Texas
- Technology
- Battery: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- IA Executed
- Queue status
- Active
- Agreement signed
- 30 January 2015
- Proposed online date
- February 2026
Location
Marker shows the centre of Webb County; the queue data does not give exact sites.
Other requests in Webb County
- SieteOnshore wind · 493 MW · agreement signed
- Cuchillas SolarSolar + storage · 306 MW · agreement signed
- Corazon Solar Phase IISolar + storage · 204 MW · agreement signed
- Corvus SolarSolar · 202 MW · agreement signed
- Seven Flags BESSBattery storage · 103 MW · agreement signed
- Cedro Hill Wind RepowerOnshore wind · 9.9 MW · agreement signed
- Outpost StorageSolar + storage · 508 MW · in study
- Siete WindOnshore wind · 493 MW · in study
- Cuchillas BESSSolar + storage · 307 MW · in study
- Cenizo SolarSolar · 301 MW · in study
- Bendito WindOnshore wind · 300 MW · in study
- Miracle Ranch Solar SLFSolar + storage · 222 MW · in study