United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Corazon Solar Phase II

Corazon Solar Phase II is a 204 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2019 (completed)
  2. ConsentedAug 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0257
Grid region
ERCOT (Texas)
Developer
BAYWA R.E. SOLAR PROJECTS
Connection point (POI)
80219 Lobo 345kV
Location
Webb County, Texas
Technology
Solar: 204 MW · Battery
Total requested
204 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
19 December 2019
Agreement signed
4 August 2020
Proposed online date
June 2028

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem