Corvus Solar

Corvus Solar is a 202 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusConsented
  1. PlanningQueued Feb 2024 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0126
Grid region
ERCOT (Texas)
Developer
Corvus Solar, LLC
Connection point (POI)
Tap 345kV Cenzio (#80219) - Lobo (#80220)
Location
Webb County, Texas
Technology
Solar: 202 MW
Total requested
202 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
7 February 2024
Agreement signed
31 July 2025
Proposed online date
November 2028

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem