🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Butcherbird Solar

Butcherbird Solar is a 116 MW solar request in interconnection study in the ERCOT interconnection queue, in Bell County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0337
Grid region
ERCOT (Texas)
Developer
Butcherbird Solar, LLC
Connection point (POI)
Tap 138 kV - Bell County #133 to Bartlett Switch #114
Location
Bell County, Texas
Technology
Solar: 116 MW
Total requested
116 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
18 December 2023
Proposed online date
February 2027

Location

Marker shows the centre of Bell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem