🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Hermes Solar

Hermes Solar is a 100 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bell County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2021 (completed)
  2. ConsentedNov 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0344
Grid region
ERCOT (Texas)
Developer
Bell 1 Solar, LLC
Connection point (POI)
Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2
Location
Bell County, Texas
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
21 September 2021
Agreement signed
8 November 2023
Proposed online date
March 2026

Location

Marker shows the centre of Bell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem