United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTHermes Solar
Hermes Solar is a 100 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bell County, Texas.
Queue statusConsented
- PlanningQueued Sep 2021 (completed)
- ConsentedNov 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0344
- Grid region
- ERCOT (Texas)
- Developer
- Bell 1 Solar, LLC
- Connection point (POI)
- Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2
- Location
- Bell County, Texas
- Technology
- Solar: 100 MW · Battery
- Total requested
- 100 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 21 September 2021
- Agreement signed
- 8 November 2023
- Proposed online date
- March 2026
Location
Marker shows the centre of Bell County; the queue data does not give exact sites.
Other requests in Bell County
- Chillingham SolarSolar · 352 MW · agreement signed
- Limewood SolarSolar + storage · 205 MW · agreement signed
- Goldeneye BESSBattery storage · 202 MW · agreement signed
- Cosper SolarSolar · 148 MW · agreement signed
- Big Elm StorageSolar + storage · 120 MW · agreement signed
- Hermes StorageSolar + storage · 100 MW · agreement signed
- Limewood StorageSolar + storage · 50.0 MW · agreement signed
- Riviera GasGas · 942 MW · in study
- Lavita BESSBattery storage · 606 MW · in study
- Bell County Morgan StorageBattery storage · 256 MW · in study
- GridGuardian BESSBattery storage · 228 MW · in study
- Bell County Leifester StorageBattery storage · 205 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem