United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTChillingham Solar
Chillingham Solar is a 352 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Bell County, Texas.
Queue statusConsented
- PlanningQueued Aug 2020 (completed)
- ConsentedFeb 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0070
- Grid region
- ERCOT (Texas)
- Developer
- Chillingham Solar LLC
- Connection point (POI)
- 3687 Bell County East 345kV
- Location
- Bell County, Texas
- Technology
- Solar: 352 MW
- Total requested
- 352 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 4 August 2020
- Agreement signed
- 4 February 2022
- Proposed online date
- February 2026
Location
Marker shows the centre of Bell County; the queue data does not give exact sites.
Other requests in Bell County
- Limewood SolarSolar + storage · 205 MW · agreement signed
- Goldeneye BESSBattery storage · 202 MW · agreement signed
- Cosper SolarSolar · 148 MW · agreement signed
- Big Elm StorageSolar + storage · 120 MW · agreement signed
- Hermes SolarSolar + storage · 100 MW · agreement signed
- Hermes StorageSolar + storage · 100 MW · agreement signed
- Limewood StorageSolar + storage · 50.0 MW · agreement signed
- Riviera GasGas · 942 MW · in study
- Lavita BESSBattery storage · 606 MW · in study
- Bell County Morgan StorageBattery storage · 256 MW · in study
- GridGuardian BESSBattery storage · 228 MW · in study
- Bell County Leifester StorageBattery storage · 205 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem