United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTSolar project IC-616, Pierce County
Solar project IC-616, Pierce County is a 118 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Pierce County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Mar 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2020 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-616
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Offerman Substation 230 kV Bus
- Location
- Pierce County, Georgia
- Technology
- Solar: 118 MW
- Total requested
- 118 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 27 March 2017
- Proposed online date
- November 2020
Location
Marker shows the centre of Pierce County; the queue data does not give exact sites.
Other requests in Pierce County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem