ONSHORE WIND · MISOOnshore wind project J1769, Howard County
Onshore wind project J1769, Howard County is a 120 MW onshore wind request in interconnection study in the MISO interconnection queue, in Howard County, Iowa, connecting to DAIRYLAND POWER COOPERATIVE.
Queue statusIn planning
- PlanningQueued Jun 2020 (current stage)
- ConsentedAug 2024 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1769
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DAIRYLAND POWER COOPERATIVE
- Connection point (POI)
- Beaver Creek to Rice 161 kV line tap (same POI as J898)
- Location
- Howard County, Iowa
- Technology
- Wind: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 25 June 2020
- Agreement signed
- 6 August 2024
- Proposed online date
- September 2026
Location
Marker shows the centre of Howard County; the queue data does not give exact sites.
Other requests in Howard County
- Onshore wind project J898, Howard CountyOnshore wind · 100 MW · under construction
- Onshore wind project J3898, Howard CountyOnshore wind · 155 MW · in study
- Onshore wind project G551, Howard CountyOnshore wind · 99.0 MW · built
- Onshore wind project J614, Howard CountyOnshore wind · 66.0 MW · built
- Solar project J1413, Howard CountySolar · 300 MW · withdrawn
- Onshore wind project G445, Howard CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1979, Howard CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G771, Howard CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J030, Howard CountyOnshore wind · 198 MW · withdrawn
- Onshore wind project G716, Howard CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project G740, Howard CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project J2466, Howard CountyOnshore wind · 130 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem