United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J030, Howard County

Onshore wind project J030, Howard County is a 198 MW onshore wind request withdrawn in the MISO interconnection queue, in Howard County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJan 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J030
Grid region
MISO (Midcontinent)
Connection point (POI)
Adams Substation
Location
Howard County, Iowa
Technology
Wind: 198 MW
Total requested
198 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
11 March 2009
Agreement signed
12 January 2011
Proposed online date
October 2010

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem