ONSHORE WIND Β· MISO

Onshore wind project G445, Howard County

Onshore wind project G445, Howard County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Howard County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2004 (completed)
  2. Withdrawn / abandonedApr 2005 (project stopped here)
  3. ConsentedApr 2005 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G445
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Howard County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
25 August 2004
Agreement signed
12 April 2005
Proposed online date
December 2005
Withdrawn
April 2005

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Howard County