United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J2466, Howard County

Onshore wind project J2466, Howard County is a 130 MW onshore wind request withdrawn in the MISO interconnection queue, in Howard County, Iowa, connecting to ITC MIDWEST.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2466
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Hazleton-Mitchell County 345kV line
Location
Howard County, Iowa
Technology
Wind: 130 MW
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 September 2022
Proposed online date
October 2027
Withdrawn
October 2025

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem