🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

BATTERY STORAGE · PJM

Battery storage project AH2-132, Salem County

Battery storage project AH2-132, Salem County is a 117 MW battery storage request in interconnection study in the PJM interconnection queue, in Salem County, New Jersey, connecting to AEC.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-132
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Chambers 230kV
Location
Salem County, New Jersey
Technology
Battery: 117 MW
Total requested
117 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
1 March 2022
Proposed online date
June 2024

Location

Marker shows the centre of Salem County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Salem County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem