United States › Grid › Interconnection queues › New Jersey
NUCLEAR · PJMNuclear project AH1-710, Salem County
Nuclear project AH1-710, Salem County is a 257 MW nuclear request in interconnection study in the PJM interconnection queue, in Salem County, New Jersey, connecting to PSEG.
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-710
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Developer
- PSEG Nuclear LLC
- Connection point (POI)
- Salem 500kV
- Location
- Salem County, New Jersey
- Technology
- Nuclear: 257 MW
- Total requested
- 257 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 9 April 2025
Location
Marker shows the centre of Salem County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Salem County
- Battery storage project AH2-333, Salem CountyBattery storage · 415 MW · in study
- Battery storage project AH2-132, Salem CountyBattery storage · 117 MW · in study
- Solar project AG2-616, Salem CountySolar · 50.0 MW · in study
- Solar project AH1-641, Salem CountySolar · 15.0 MW · in study
- Pilesgrove Solar ProjectSolar · 149 MW · suspended
- Salem 1 & 2Nuclear · 115 MW · built
- Hope Creek 1Nuclear · 78.0 MW · built
- Hope Creek 1Nuclear · 69.0 MW · built
- Hope Creek Generating StationNuclear · 50.0 MW · built
- Hope Creek 1Nuclear · 43.0 MW · built
- Salem 1 & 2Nuclear · 26.0 MW · built
- Pilesgrove SPSolar · 19.9 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem