Hope Creek 1

Hope Creek 1 is a 69.0 MW nuclear request built and operating in the PJM interconnection queue, in Salem County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jan 2000 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2001 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
C08
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Hope Creek 500kV
Location
Salem County, New Jersey
Technology
Nuclear: 69.0 MW
Total requested
69.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
31 January 2000
Proposed online date
August 2001
Came online
August 2001

Location

Marker shows the centre of Salem County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Salem County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem