NUCLEAR Β· PJM

Salem 1 & 2

Salem 1 & 2 is a 115 MW nuclear request built and operating in the PJM interconnection queue, in Salem County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jan 2002 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
H17
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Salem 500kV
Location
Salem County, New Jersey
Technology
Nuclear: 115 MW
Total requested
115 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
11 January 2002
Proposed online date
June 2008
Came online
June 2008

Location

Marker shows the centre of Salem County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Salem County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem