Battery storage project AH2-333, Salem County

Battery storage project AH2-333, Salem County is a 415 MW battery storage request in interconnection study in the PJM interconnection queue, in Salem County, New Jersey, connecting to AEC.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-333
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Orchard 230kV
Location
Salem County, New Jersey
Technology
Battery: 415 MW
Total requested
415 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
11 March 2022
Proposed online date
December 2025

Location

Marker shows the centre of Salem County; the queue data does not give exact sites.