OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 130

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 130 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J1635, Branch County
Battery storage
100 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Solar + storage project 718, Blaine County
Solar + storage · Moonstone Energy, LLC
100 MWAgreement signed Blaine, IDWest Jun 2023target 2028
Solar project IA-PNM-2018-03, San Juan County
Solar · DESRI Rockmont Development
100 MWPaused / redesign San Juan, NMWest Jul 2018target 2021
Surplus; J758
Other
100 MWIn study Calhoun, MIMISO Aug 2024target 2027
Solar + storage project J2193, Waushara County
Solar + storage
100 MWIn study Waushara, WIMISO Nov 2021target 2024
Surplus; J1190
Battery storage
100 MWIn study Lagrange, INMISO Jul 2025target 2027
Battery storage project 15, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Dec 2021target 2027
Sunsetter BESS
Battery storage · CED Development Inc.
100 MWIn study Uvalde, TXERCOT Feb 2021target 2027
Solar project J1795, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Jun 2020target 2025
Battery storage project AH2-122, Lee County
Battery storage
100 MWIn study Lee, ILPJM Feb 2022target 2028
Battery storage project J2195, Fayette County
Battery storage
100 MWIn study Fayette, ILMISO Jan 2025target 2024
Battery storage project AH2-217, Morrow County
Battery storage
100 MWIn study Morrow, OHPJM Mar 2022target 2026
Solar project Company HL, Lander County
Solar
100 MWAgreement signed Lander, NVWest Mar 2017target 2023
Battery storage project Company JW, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2019target 2027
Other project J4183
Other
99.9 MWIn study MISO target 2027
Cartersville Solar
Solar
99.9 MWPaused / redesign Powhatan, VAPJM Mar 2017target 2026
Solar project AH2-078, Charlotte County
Solar
99.7 MWIn study Charlotte, VAPJM Jan 2022target 2025
Brandonville Solar
Solar
99.6 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Adam Bryant BESS
Battery storage · Adam Bryant BESS LLC
99.5 MWIn study Medina, TXERCOT Feb 2024target 2027
Azalea
Solar + storage
99.3 MWAgreement signed Kern, CACAISO Apr 2018target 2025
Noosa Energy Storage
Battery storage
99.0 MWAgreement signed San Joaquin, CACAISO Apr 2019target 2029
Solar project J1232, Coles County
Solar
99.0 MWAgreement signed Coles, ILMISO Apr 2019target 2025
Rippon
Solar
99.0 MWAgreement signed Jefferson, WVPJM Mar 2019target 2026
Battery storage project 956240, Rutherford County
Battery storage
99.0 MWIn study Rutherford, NCSoutheast Jun 2024
Battery storage project 976971, Iredell County
Battery storage
99.0 MWIn study Iredell, NCSoutheast Jun 2025
Battery storage project J4172, Wapello County
Battery storage
99.0 MWIn study Wapello, IAMISO Oct 2025target 2028
Solar + storage project AH1-216, Isle Of Wight County
Solar + storage · Boykin Solar Center, LLC
99.0 MWIn study Isle Of Wight, VAPJM Feb 2025target 2025
Solar project J1266, Marion County
Solar
99.0 MWAgreement signed Marion, ILMISO Apr 2019target 2025
Solar project J1294, Sunflower County
Solar
99.0 MWUnder construction Sunflower, MSMISO Apr 20192024
Solar project 634, Beaver County
Solar · Fremont Solar, LLC
99.0 MWAgreement signed Beaver, UTWest Nov 2014target 2025
Battery storage project 956244, Robeson County
Battery storage · Duke Energy Progress, LLC.
99.0 MWIn study Robeson, NCSoutheast Jun 2024
Solar project C2-169, Tooele County
Solar · PacifiCorp
99.0 MWPaused / redesign Tooele, UTWest May 2022target 2026
Onshore wind project J1483, Iowa County
Onshore wind
99.0 MWAgreement signed Iowa, WIMISO Apr 2019target 2026
Solar project LGE-GIS-2019-025, Mercer County
Solar
99.0 MWAgreement signed Mercer, KYSoutheast May 2019target 2026
Battery storage project 977308, Spartanburg County
Battery storage
99.0 MWIn study Spartanburg, SCSoutheast Jun 2025
Battery storage project 977302, York County
Battery storage
99.0 MWIn study York, SCSoutheast Jun 2025
Solar project J1993, Columbia County
Solar
99.0 MWIn study Columbia, WIMISO Dec 2021target 2025
Battery storage project 977315, Greenwood County
Battery storage
99.0 MWIn study Greenwood, SCSoutheast Jun 2025
Solar project 660, Jackson County
Solar
99.0 MWIn study Jackson, ALSoutheast Oct 2024target 2032
Solar project 636, Iron County
Solar · Rush Lake Solar, LLC
99.0 MWAgreement signed Iron, UTWest Dec 2014target 2025
Battery storage project PP00026, Robeson County
Battery storage
99.0 MWIn study Robeson, NCSoutheast Apr 2025target 2029
Onshore wind project GI-1505, Brown County
Onshore wind
99.0 MWIn study Brown, SDWest Apr 2015
Solar project J2208, De Soto Parish County
Solar
99.0 MWIn study De Soto Parish, LAMISO Aug 2021target 2024
Onshore wind project J1508, Marathon County
Onshore wind
98.9 MWAgreement signed Marathon, WIMISO Jun 2020target 2026
Onshore wind project GEN-2016-087, Campbell County
Onshore wind
98.9 MWAgreement signed Campbell, SDSPP Jul 2016target 2026
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4
Other
98.8 MWIn study St. Louis, MOMISO Dec 2024target 2025
Cannibal Draw Storage
Solar + storage · Cannibal Draw Solar, LLC
98.6 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Solar project J1377, Rock County
Solar
98.6 MWAgreement signed Rock, WIMISO Apr 2019target 2025
Leitrim 1 Solar
Solar · Leitsol LLC
98.4 MWIn study Hill, TXERCOT Jan 2021target 2027
Solar project J1732, Columbia County
Solar
98.4 MWAgreement signed Columbia, WIMISO Jun 2020target 2025
Page 130 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)