United States › Grid › Interconnection queues › Wisconsin
ONSHORE WIND · MISOOnshore wind project J1483, Iowa County
Onshore wind project J1483, Iowa County is a 99.0 MW onshore wind request with a signed interconnection agreement in the MISO interconnection queue, in Iowa County, Wisconsin, connecting to American Transmission Co..
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedJan 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1483
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Hill Valley 345 kV Substation
- Location
- Iowa County, Wisconsin
- Technology
- Wind: 99.0 MW
- Total requested
- 99.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 26 January 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Iowa County; the queue data does not give exact sites.
Other requests in Iowa County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem