United States › Grid › Interconnection queues › Idaho

SOLAR + STORAGE · WEST

Solar + storage project 718, Blaine County

Solar + storage project 718, Blaine County is a 100 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Blaine County, Idaho, connecting to Idaho Power Company.

Queue statusConsented
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
718
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Moonstone Energy, LLC
Connection point (POI)
Moonstone Substation 138kV
Location
Blaine County, Idaho
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
1 June 2023
Agreement signed
30 April 2025
Proposed online date
June 2028

Location

Marker shows the centre of Blaine County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Blaine County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem