United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J1294, Sunflower County
Solar project J1294, Sunflower County is a 99.0 MW solar request under construction in the MISO interconnection queue, in Sunflower County, Mississippi, connecting to ENTERGY MISSISSIPPI.
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedJan 2022 (completed)
- Construction (current stage)
- OperatingAug 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1294
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI
- Connection point (POI)
- Indianola - Cleveland 115kV Line
- Location
- Sunflower County, Mississippi
- Technology
- Solar: 99.0 MW
- Total requested
- 99.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 25 January 2022
- Proposed online date
- December 2023
- Came online
- August 2024
Location
Marker shows the centre of Sunflower County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Sunflower County
- Solar project J604, Sunflower CountySolar · 100 MW · agreement signed
- Onshore wind project J3623, Sunflower CountyOnshore wind · 350 MW · in study
- Solar project J2289, Sunflower CountySolar · 200 MW · in study
- Solar project J4189, Sunflower CountySolar · 200 MW · in study
- Onshore wind project J3900, Sunflower CountyOnshore wind · 163 MW · in study
- Solar project J2740, Sunflower CountySolar · 150 MW · in study
- Solar + storage project J2869, Sunflower CountySolar + storage · 150 MW · in study
- Solar + storage project J2763, Sunflower CountySolar + storage · 100 MW · in study
- Solar project J2297, Sunflower CountySolar · 100 MW · in study
- Onshore wind project J3592, Sunflower CountyOnshore wind · 57.0 MW · in study
- Solar project J3774, Sunflower CountySolar · 303 MW · withdrawn
- Onshore wind project J686, Sunflower CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem