🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Mississippi

SOLAR · MISO

Solar project J2740, Sunflower County

Solar project J2740, Sunflower County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Sunflower County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2740
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
DELTA SWYD - SHELBY SS 115.0kV
Location
Sunflower County, Mississippi
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 September 2022
Proposed online date
February 2029

Location

Marker shows the centre of Sunflower County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Sunflower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem