SOLAR + STORAGE · MISO

Solar + storage project J2763, Sunflower County

Solar + storage project J2763, Sunflower County is a 100 MW solar + storage request in interconnection study in the MISO interconnection queue, in Sunflower County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2763
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
CLEVELAND/SOUTH - STEINER (CE) 115.0kV
Location
Sunflower County, Mississippi
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
14 September 2022
Proposed online date
December 2025

Location

Marker shows the centre of Sunflower County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Sunflower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem