Azalea

Azalea is a 99.3 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedJun 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1493
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Arco 70 kV
Location
Kern County, California
Technology
Solar: 61.3 MW · Battery: 38.0 MW
Total requested
99.3 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
16 April 2018
Agreement signed
11 June 2020
Proposed online date
September 2025

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem