United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J1795, Acadia Parish County
Solar project J1795, Acadia Parish County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Acadia Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
- PlanningQueued Jun 2020 (current stage)
- ConsentedOct 2024 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1795
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Bayou Cove to Richard 138kV (Circuit 258)
- Location
- Acadia Parish County, Louisiana
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 22 June 2020
- Agreement signed
- 21 October 2024
- Proposed online date
- December 2025
Location
Marker shows the centre of Acadia Parish County; the queue data does not give exact sites.
Other requests in Acadia Parish County
- Solar project J1794, Acadia Parish CountySolar · 150 MW · agreement signed
- Solar project J1561, Acadia Parish CountySolar · 75.0 MW · agreement signed
- Solar project J2249, Acadia Parish CountySolar · 144 MW · in study
- Solar project J2715, Acadia Parish CountySolar · 120 MW · in study
- Solar project J1904, Acadia Parish CountySolar · 100 MW · in study
- Solar project J3513, Acadia Parish CountySolar · 550 MW · withdrawn
- Solar project J1462, Acadia Parish CountySolar · 150 MW · withdrawn
- Battery storage project J2568, Acadia Parish CountyBattery storage · 120 MW · withdrawn
- Solar project J2858, Acadia Parish CountySolar · 110 MW · withdrawn
- Solar project J566, Acadia Parish CountySolar · 102 MW · withdrawn
- Solar + storage project J2616, Acadia Parish CountySolar + storage · 100 MW · withdrawn
- Solar project J675, Acadia Parish CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem