SOLAR · MISO

Solar project J1904, Acadia Parish County

Solar project J1904, Acadia Parish County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Acadia Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1904
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Richard 138 kV
Location
Acadia Parish County, Louisiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
17 August 2021
Agreement signed
8 December 2025
Proposed online date
November 2028

Location

Marker shows the centre of Acadia Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Acadia Parish County