SOLAR · MISO

Solar project J1794, Acadia Parish County

Solar project J1794, Acadia Parish County is a 150 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Acadia Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusConsented
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedNov 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1794
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
RICHARD - SCOTT 138.0kV
Location
Acadia Parish County, Louisiana
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
22 June 2020
Agreement signed
18 November 2022
Proposed online date
May 2025

Location

Marker shows the centre of Acadia Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Acadia Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem