πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

SOLAR Β· MISO

Solar project J675, Acadia Parish County

Solar project J675, Acadia Parish County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Acadia Parish County, Louisiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandonedNov 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J675
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Acadia Parish County, Louisiana
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
11 July 2016
Proposed online date
September 2019
Withdrawn
November 2016

Location

Marker shows the centre of Acadia Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Acadia Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem