ONSHORE WIND · MISO

Onshore wind project J1508, Marathon County

Onshore wind project J1508, Marathon County is a 98.9 MW onshore wind request with a signed interconnection agreement in the MISO interconnection queue, in Marathon County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusConsented
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedSep 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1508
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
B-54 Wien to McMillan 115KV
Location
Marathon County, Wisconsin
Technology
Wind: 98.9 MW
Total requested
98.9 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
19 June 2020
Agreement signed
23 September 2024
Proposed online date
September 2026

Location

Marker shows the centre of Marathon County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Marathon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem