United States › Grid › Interconnection queues › Wisconsin

ONSHORE WIND · MISO

Onshore wind project J3469, Marathon County

Onshore wind project J3469, Marathon County is a 100 MW onshore wind request in interconnection study in the MISO interconnection queue, in Marathon County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3469
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Stratford - McMillan 115.0kV
Location
Marathon County, Wisconsin
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
16 April 2024
Proposed online date
June 2026

Location

Marker shows the centre of Marathon County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Marathon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem