Solar project J1121, Marathon County

Solar project J1121, Marathon County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Marathon County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMay 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1121
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Stone Lake - (Pershing) - Gardner Park 345 kV Line Tap
Location
Marathon County, Wisconsin
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2021
Withdrawn
May 2020

Location

Marker shows the centre of Marathon County; the queue data does not give exact sites.