United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project G420, Marathon County

Onshore wind project G420, Marathon County is a 99.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Marathon County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2004 (completed)
  2. Withdrawn / abandonedNov 2004 (project stopped here)
  3. ConsentedNov 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G420
Grid region
MISO (Midcontinent)
Connection point (POI)
Wien 115kV
Location
Marathon County, Wisconsin
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
22 March 2004
Agreement signed
8 November 2004
Proposed online date
May 2008
Withdrawn
November 2004

Location

Marker shows the centre of Marathon County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Marathon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem