United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
BATTERY STORAGE Β· MISOBattery storage project J2439, Marathon County
Battery storage project J2439, Marathon County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Marathon County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2439
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Gardner Park-Stone Lake 345kV
- Location
- Marathon County, Wisconsin
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 September 2022
- Proposed online date
- October 2028
- Withdrawn
- July 2025
Location
Marker shows the centre of Marathon County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Marathon County
- Onshore wind project J1508, Marathon CountyOnshore wind Β· 98.9 MW Β· agreement signed
- Solar project J4069, Marathon CountySolar Β· 170 MW Β· in study
- Onshore wind project J3469, Marathon CountyOnshore wind Β· 100 MW Β· in study
- Coal project G144, Marathon CountyCoal Β· 550 MW Β· built
- Coal project G523, Marathon CountyCoal Β· 550 MW Β· withdrawn
- Onshore wind project J1085, Marathon CountyOnshore wind Β· 300 MW Β· withdrawn
- Solar project J1121, Marathon CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project J2345, Marathon CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project J821, Marathon CountyOnshore wind Β· 99.9 MW Β· withdrawn
- Onshore wind project G420, Marathon CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Other project G112, Marathon CountyOther Β· 85.0 MW Β· withdrawn
- Other project J040, Marathon CountyOther Β· 50.0 MW Β· withdrawn