SOLAR · WESTSolar project 634, Beaver County
Solar project 634, Beaver County is a 99.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Nov 2014 (completed)
- ConsentedSep 2016 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 634
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Fremont Solar, LLC
- Connection point (POI)
- Parowan-Sigurd line
- Location
- Beaver County, Utah
- Technology
- Solar: 99.0 MW
- Total requested
- 99.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA signed 9/9/16, Suspended 10/31/16, unsuspended 10/30/19
- Queue status
- Active
- Entered queue
- 20 November 2014
- Agreement signed
- 9 September 2016
- Proposed online date
- December 2025
Location
Marker shows the centre of Beaver County; the queue data does not give exact sites.
Other requests in Beaver County
- Battery storage project S0008, Beaver CountyBattery storage · 80.0 MW · agreement signed
- Battery storage project S0007, Beaver CountyBattery storage · 80.0 MW · agreement signed
- Battery storage project S0009, Beaver CountyBattery storage · 80.0 MW · agreement signed
- Geothermal project T2-012, Beaver CountyGeothermal · 3.6 MW · in study
- Solar project 631, Beaver CountySolar · 99.0 MW · built
- Solar project 551, Beaver CountySolar · 80.0 MW · built
- Solar project 515, Beaver CountySolar · 80.0 MW · built
- Solar project 516, Beaver CountySolar · 80.0 MW · built
- Geothermal project 313, Beaver CountyGeothermal · 25.0 MW · built
- Geothermal project 66, Beaver CountyGeothermal · 15.0 MW · built
- Geothermal project 415, Beaver CountyGeothermal · 11.0 MW · built
- Other project 333, Beaver CountyOther · 3.2 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem