Solar project 634, Beaver County

Solar project 634, Beaver County is a 99.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Nov 2014 (completed)
  2. ConsentedSep 2016 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
634
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Fremont Solar, LLC
Connection point (POI)
Parowan-Sigurd line
Location
Beaver County, Utah
Technology
Solar: 99.0 MW
Total requested
99.0 MW
Service type
Energy only (ERIS)
Study phase
IA signed 9/9/16, Suspended 10/31/16, unsuspended 10/30/19
Queue status
Active
Entered queue
20 November 2014
Agreement signed
9 September 2016
Proposed online date
December 2025

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem