BATTERY STORAGE · WESTBattery storage project S0008, Beaver County
Battery storage project S0008, Beaver County is a 80.0 MW battery storage request with a signed interconnection agreement in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Mar 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- S0008
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Escalante BESS II LLC
- Connection point (POI)
- Hickory substation
- Location
- Beaver County, Utah
- Technology
- Battery: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed SLGIA 3/25/2024, suspended 5/8/2025, unsuspended 11/4/2025
- Queue status
- Active
- Entered queue
- 23 March 2022
- Proposed online date
- August 2024
Location
Marker shows the centre of Beaver County; the queue data does not give exact sites.
Other requests in Beaver County
- Solar project 634, Beaver CountySolar · 99.0 MW · agreement signed
- Battery storage project S0007, Beaver CountyBattery storage · 80.0 MW · agreement signed
- Battery storage project S0009, Beaver CountyBattery storage · 80.0 MW · agreement signed
- Geothermal project T2-012, Beaver CountyGeothermal · 3.6 MW · in study
- Solar project 631, Beaver CountySolar · 99.0 MW · built
- Solar project 551, Beaver CountySolar · 80.0 MW · built
- Solar project 515, Beaver CountySolar · 80.0 MW · built
- Solar project 516, Beaver CountySolar · 80.0 MW · built
- Geothermal project 313, Beaver CountyGeothermal · 25.0 MW · built
- Geothermal project 66, Beaver CountyGeothermal · 15.0 MW · built
- Geothermal project 415, Beaver CountyGeothermal · 11.0 MW · built
- Other project 333, Beaver CountyOther · 3.2 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem