Other project 333, Beaver County

Other project 333, Beaver County is a 3.2 MW other request built and operating in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued May 2010 (completed)
  2. ConsentedFeb 2012 (completed)
  3. Construction (completed)
  4. OperatingTarget Aug 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
333
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Blue Mountain Biogas, LLC
Connection point (POI)
Circuit SML21, out of South Milford substation
Location
Beaver County, Utah
Technology
Other: 3.2 MW
Total requested
3.2 MW
Service type
Energy only (ERIS)
Study phase
IA signed 2/27/12
Queue status
Operational
Entered queue
17 May 2010
Agreement signed
27 February 2012
Proposed online date
August 2012

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem