🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · MISO

Surplus; J1190

Surplus; J1190 is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Lagrange County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1108
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
LAGRANGE
Location
Lagrange County, Indiana
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Active
Entered queue
18 July 2025
Proposed online date
June 2027

Location

Marker shows the centre of Lagrange County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Lagrange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem