United States βΊ Grid βΊ Interconnection queues βΊ Indiana
ONSHORE WIND Β· PJMOnshore wind project Y2-107, Lagrange County
Onshore wind project Y2-107, Lagrange County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Lagrange County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2012 (completed)
- Withdrawn / abandonedAug 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Y2-107
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Robison Park-Argenta 345 kV
- Location
- Lagrange County, Indiana
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 2 November 2012
- Proposed online date
- November 2015
- Withdrawn
- August 2013
Location
Marker shows the centre of Lagrange County; the queue data does not give exact sites.
Other requests in Lagrange County
- Solar project J1392, Lagrange CountySolar Β· 100 MW Β· agreement signed
- Battery storage project J1323, Lagrange CountyBattery storage Β· 25.0 MW Β· agreement signed
- Battery storage project J3291, Lagrange CountyBattery storage Β· 200 MW Β· in study
- Surplus; J1190Battery storage Β· 100 MW Β· in study
- Onshore wind project R61, Lagrange CountyOnshore wind Β· 350 MW Β· withdrawn
- Solar + storage project J3664, Lagrange CountySolar + storage Β· 80.0 MW Β· withdrawn
- Solar project J1265, Lagrange CountySolar Β· 43.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem