🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

SOLAR · MISO

Solar project J1392, Lagrange County

Solar project J1392, Lagrange County is a 100 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Lagrange County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJun 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1392
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Lagrange 138 kV Substation
Location
Lagrange County, Indiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
15 June 2023
Proposed online date
June 2025

Location

Marker shows the centre of Lagrange County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Lagrange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem