United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project J1323, Lagrange County
Battery storage project J1323, Lagrange County is a 25.0 MW battery storage request with a signed interconnection agreement in the MISO interconnection queue, in Lagrange County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedJun 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1323
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- Lagrange 138 kV Substation
- Location
- Lagrange County, Indiana
- Technology
- Battery: 25.0 MW
- Total requested
- 25.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 15 June 2023
- Proposed online date
- June 2025
Location
Marker shows the centre of Lagrange County; the queue data does not give exact sites.
Other requests in Lagrange County
- Solar project J1392, Lagrange CountySolar · 100 MW · agreement signed
- Battery storage project J3291, Lagrange CountyBattery storage · 200 MW · in study
- Surplus; J1190Battery storage · 100 MW · in study
- Onshore wind project R61, Lagrange CountyOnshore wind · 350 MW · withdrawn
- Onshore wind project Y2-107, Lagrange CountyOnshore wind · 200 MW · withdrawn
- Solar + storage project J3664, Lagrange CountySolar + storage · 80.0 MW · withdrawn
- Solar project J1265, Lagrange CountySolar · 43.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem