United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 69

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 69 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AG2-329, Wyandot County
Battery storage · Wombat Solar LLC
200 MWIn study Wyandot, OHPJM Mar 2025target 2024
Solar + storage project AH2-025, Fountain County
Solar + storage
200 MWIn study Fountain, INPJM Oct 2021target 2027
Surplus; J944
Battery storage
200 MWIn study New Madrid, MOMISO Aug 2025target 2028
Battery storage project Company 248, Clark County
Battery storage
200 MWAgreement signed Clark, NVWest Mar 2023target 2030
Onshore wind project BHBE G21, Campbell County
Onshore wind
200 MWAgreement signed Campbell, SDWest Aug 2022target 2025
Solar + storage project IC-839, Sumter County
Solar + storage
200 MWAgreement signed Sumter, GASoutheast Nov 2019target 2027
Solar project J1772, White County
Solar
200 MWIn study White, INMISO Jun 2020target 2026
Battery storage project 98, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Mar 2021target 2026
Battery storage project GI-SISS-2025-06, Logan County
Battery storage
200 MWIn study Logan, COWest Oct 2025target 2027
Battery storage project Q409, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2021target 2025
Battery storage project Company 202, Clark County
Battery storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Solar + storage project IA-PNM-2023-22, Santa Fe County
Solar + storage
200 MWIn study Santa Fe, NMWest Sep 2023target 2028
Battery storage project 23-239, Multnomah County
Battery storage
200 MWIn study Multnomah, ORWest Dec 2023target 2028
Battery storage project Q291, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2018target 2023
Battery storage project J3236, Chisago County
Battery storage
200 MWIn study Chisago, MNMISO Mar 2024target 2028
Solar project J2672, Shiawassee County
Solar
200 MWIn study Shiawassee, MIMISO Sep 2022target 2025
Solar + storage project 2024-G8, Clark County
Solar + storage
200 MWIn study Clark, NVWest Dec 2024target 2028
Kestrel Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2027
Onshore wind project 11-040, Gilliam County
Onshore wind
200 MWPaused / redesign Gilliam, ORWest Mar 2011target 2015
Solar project J2877, Midland County
Solar
200 MWIn study Midland, MIMISO Sep 2022target 2025
Onshore wind project 09-033, Wasco County
Onshore wind
200 MWPaused / redesign Wasco, ORWest Jan 2009target 2013
Fairboro Solar
Solar
200 MWIn study Ware, GASoutheast Dec 2021target 2023
Onshore wind project GI-2006-2, Logan County
Onshore wind
200 MWAgreement signed Logan, COWest Jun 2006target 2008
Solar project J3880, Clay County
Solar
200 MWIn study Clay, ILMISO Feb 2025target 2030
Solar + storage project J2238, Maries County
Solar + storage
200 MWIn study Maries, MOMISO Jul 2025target 2024
Battery storage project 149, Whatcom County
Battery storage
200 MWIn study Whatcom, WAWest Apr 2024target 2027
Solar project J1870, Tangipahoa Parish County
Solar
200 MWIn study Tangipahoa Parish, LAMISO Aug 2021target 2028
Solar + storage project LGE-GIS-2021-009, Hardin County
Solar + storage
200 MWPaused / redesign Hardin, KYSoutheast Mar 2021target 2026
Onshore wind project GI-2011-7, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest Aug 2011target 2012
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Solar + storage project Company LZ, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Solar project J1460, Rock County
Solar
200 MWUnder construction Rock, WIMISO Apr 2019target 2025
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Solar project GEN-2024-234, Burt County
Solar
200 MWIn study Burt, NESPP Mar 2025target 2029
Surplus; J416
Battery storage
200 MWIn study Franklin, IAMISO Aug 2025target 2026
Wind + storage project J3230, Crittenden County
Wind + storage
200 MWIn study Crittenden, ARMISO Sep 2022target 2025
Solar project J2538, Clark County
Solar
200 MWIn study Clark, INMISO Oct 2025target 2026
Onshore wind project J3849, Winnebago County
Onshore wind
200 MWIn study Winnebago, IAMISO Dec 2024target 2030
Onshore wind project J2641, Jackson County
Onshore wind
200 MWIn study Jackson, ARMISO Sep 2022target 2025
Battery storage project J2213, Marshall County
Battery storage
200 MWIn study Marshall, INMISO Mar 2022target 2028
Solar project J4189, Sunflower County
Solar
200 MWIn study Sunflower, MSMISO Oct 2025target 2030
Onshore wind project J2614, Henry County
Onshore wind
200 MWIn study Henry, ILMISO Sep 2022target 2026
Solar project J3891, Pope County
Solar
200 MWIn study Pope, ARMISO Jan 2025target 2030
Solar + storage project J2265, Bollinger County
Solar + storage
200 MWIn study Bollinger, MOMISO Jul 2025target 2024
Solar project J2967, Jefferson Davis Parish County
Solar
200 MWIn study Jefferson Davis Parish, LAMISO Sep 2022target 2025
Other project Q585, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2030
Onshore wind project GI-2007-6, Weld County
Onshore wind
200 MWAgreement signed Weld, COWest Mar 2007target 2008
Battery storage project J3497, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Apr 2024target 2028
Garnet Energy Center
Solar · Garnet Energy Center, LLC
200 MWIn study Cayuga, NYNYISO Jun 2019target 2028
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Page 69 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)