🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oregon

ONSHORE WIND · WEST

Onshore wind project 09-033, Wasco County

Onshore wind project 09-033, Wasco County is a 200 MW onshore wind request suspended in the West interconnection queue, in Wasco County, Oregon, connecting to Portland General Electric.

Queue statusPaused / redesign
  1. PlanningQueued Jan 2009 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2013 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
09-033
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
A new location on/near Warm Springs Reservation
Location
Wasco County, Oregon
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
5 January 2009
Proposed online date
June 2013

Location

Marker shows the centre of Wasco County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Wasco County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem