United States › Grid › Interconnection queues › Oregon
SOLAR · WESTSolar project G0524, Wasco County
Solar project G0524, Wasco County is a 20.0 MW solar request in interconnection study in the West interconnection queue, in Wasco County, Oregon.
Queue statusIn planning
- PlanningQueued Jan 2016 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2018 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G0524
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Within 2 miles of Wasco Electric Coop's 69 kV Tygh Valley Substation (Tap or new substation)
- Location
- Wasco County, Oregon
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 7 January 2016
- Proposed online date
- December 2018
Location
Marker shows the centre of Wasco County; the queue data does not give exact sites.
Other requests in Wasco County
- Solar + storage project G0681, Wasco CountySolar + storage · 2,000 MW · in study
- Battery storage project G1055, Wasco CountyBattery storage · 1,300 MW · in study
- Solar + storage project G0773, Wasco CountySolar + storage · 1,300 MW · in study
- Solar + storage project G0797, Wasco CountySolar + storage · 1,300 MW · in study
- Other project G0787, Wasco CountyOther · 1,200 MW · in study
- Battery storage project G0774, Wasco CountyBattery storage · 650 MW · in study
- Onshore wind project G0619, Wasco CountyOnshore wind · 500 MW · in study
- Onshore wind project G0974, Wasco CountyOnshore wind · 250 MW · in study
- Solar project G0367, Wasco CountySolar · 202 MW · in study
- Onshore wind project G0345, Wasco CountyOnshore wind · 201 MW · in study
- Solar project G0368, Wasco CountySolar · 101 MW · in study
- Solar project G0523, Wasco CountySolar · 13.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem