SOLAR · MISO

Solar project J956, Ralls County

Solar project J956, Ralls County is a 200 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Ralls County, Missouri, connecting to Ameren Missouri.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedDec 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingDec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J956
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Spencer Creek 345kV Substation
Location
Ralls County, Missouri
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
9 March 2018
Agreement signed
22 December 2021
Proposed online date
June 2024
Came online
December 2024

Location

Marker shows the centre of Ralls County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri