SOLAR · MISOSolar project J956, Ralls County
Solar project J956, Ralls County is a 200 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Ralls County, Missouri, connecting to Ameren Missouri.
Queue statusConsented
- PlanningQueued Mar 2018 (completed)
- ConsentedDec 2021 (current stage)
- Construction (not yet reached)
- OperatingDec 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J956
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Ameren Missouri
- Connection point (POI)
- Spencer Creek 345kV Substation
- Location
- Ralls County, Missouri
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 9 March 2018
- Agreement signed
- 22 December 2021
- Proposed online date
- June 2024
- Came online
- December 2024
Location
Marker shows the centre of Ralls County; the queue data does not give exact sites.
Other requests in Ralls County
- Solar project J2288, Ralls CountySolar · 175 MW · in study
- Solar project GI-127, Ralls CountySolar · 80.0 MW · in study
- Other project J1489, Ralls CountyOther · 500 MW · withdrawn
- Onshore wind project GEN-2018-041, Ralls CountyOnshore wind · 400 MW · withdrawn
- Solar project J1222, Ralls CountySolar · 200 MW · withdrawn
- Solar project J3720, Ralls CountySolar · 200 MW · withdrawn
- Onshore wind project GEN-2018-040, Ralls CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem