πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· SPP

Onshore wind project GEN-2018-040, Ralls County

Onshore wind project GEN-2018-040, Ralls County is a 100 MW onshore wind request withdrawn in the SPP interconnection queue, in Ralls County, Missouri, connecting to KCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandonedAug 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-040
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Sibley - Overton 345kV Line Break
Location
Ralls County, Missouri
Technology
Wind: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 May 2018
Proposed online date
December 2025
Came online
December 2025
Withdrawn
August 2022

Location

Marker shows the centre of Ralls County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Ralls County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem