United States βΊ Grid βΊ Interconnection queues βΊ Missouri
ONSHORE WIND Β· SPPOnshore wind project GEN-2018-041, Ralls County
Onshore wind project GEN-2018-041, Ralls County is a 400 MW onshore wind request withdrawn in the SPP interconnection queue, in Ralls County, Missouri, connecting to KCPL.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedAug 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2018-041
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- KCPL
- Connection point (POI)
- Sibley - Overton 345kV Line Break
- Location
- Ralls County, Missouri
- Technology
- Wind: 400 MW
- Total requested
- 400 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 May 2018
- Proposed online date
- December 2025
- Came online
- December 2025
- Withdrawn
- August 2022
Location
Marker shows the centre of Ralls County; the queue data does not give exact sites.
Other requests in Ralls County
- Solar project J956, Ralls CountySolar Β· 200 MW Β· agreement signed
- Solar project J2288, Ralls CountySolar Β· 175 MW Β· in study
- Solar project GI-127, Ralls CountySolar Β· 80.0 MW Β· in study
- Other project J1489, Ralls CountyOther Β· 500 MW Β· withdrawn
- Solar project J1222, Ralls CountySolar Β· 200 MW Β· withdrawn
- Solar project J3720, Ralls CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2018-040, Ralls CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem