SOLAR · MISO

Solar project J1772, White County

Solar project J1772, White County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in White County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. ConsentedOct 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1772
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Reynolds 345KV
Location
White County, Indiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
22 June 2020
Agreement signed
8 October 2025
Proposed online date
March 2026

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in White County